Inexplicably frozen’: Judge quashes Ottawa’s Coalspur order as it failed to consult with Ermineskin Cree Nation – Financial Post

Inexplicably frozen’: Judge quashes Ottawa’s Coalspur order as it failed to consult with Ermineskin Cree Nation – Financial Post

by ahnationtalk on July 23, 2021117 Views

Jul 23, 2021

Comes just weeks after a federal policy statement on thermal coal all but sent Coalspur’s Vista expansion up in smoke

Coalspur Mines Ltd.’s controversial Vista mine expansion project is no longer subject to the federal impact assessment process, a federal judge ruled this week.

The Federal Court ruling quashed a June 2020 designation order from Environment and Climate Change Minister Jonathan Wilkinson that subjected both Vista’s proposed open-pit expansion and underground test mine to review by the federal impact assessment agency.

Read More: https://financialpost.com/commodities/energy/inexplicably-frozen-judge-quashes-ottawas-coalspur-order-as-it-failed-to-consult-with-ermineskin-cree-nation

Send To Friend Email Print Story