PureGold Mine Ramp-Up Progressing Steadily

PureGold Mine Ramp-Up Progressing Steadily

by ahnationtalk on March 3, 202153 Views

March 3, 2021

VANCOUVER, B.C. – Pure Gold Mining Inc. (TSX-V:PGM, LSE:PUR) (“PureGold” or the “Company”), is pleased to provide an update on ongoing commissioning and ramp-up activities at the Company’s high grade PureGold Mine in Red Lake, Ontario.

Since pouring first gold in December 2020, commissioning activities at the PureGold Mine have transitioned to full scale ramp-up of the mining and milling operations, with approximately 260 persons employed at the mine site. Performance to date has met or exceeded expectations with respect to underground development and ore production rates, milling performance and gold recovery. Gold pours and shipments have continued regularly throughout the ramp-up period.

Mine Production

The underground mine is currently being accessed via a single decline, the Main Ramp, which is presently at a depth of approximately 300 metres. Ore production to date has primarily been from lateral sill development with the establishment of access to longhole and mechanized cut and fill stopes being a key priority during ramp-up. The first high grade stopes began to come into production in late February and head grades to the mill have increased since that time. With significant lateral sill development now complete, high grade stopes are expected to comprise an increasing proportion of ore production over the coming months. Accordingly, head grades are expected to continue to increase and unit costs are expected to continue trending downward. The forecast grade of mine production for the month of March is 7.0 g/t gold, in line with the grade profile for the first year of production outlined in the 2019 Feasibility Study.1

East Portal

To allow for increased ore tonnage from the mine and enhanced flexibility, a second decline on the northeast end of the mine, the East Portal, was collared in 2020 and is currently advancing at a rate of over seven metres per day. Lateral sill development from the East Portal is expected to commence in late March 2021 with stope production anticipated from April onward. Ore production from the East Portal will complement current ore production from the Main Ramp and with two independent mining centers established, the Company expects to be able to meet or exceed the design capacity of 800 tonnes per day from the mine.

Processing

The milling facility has performed in line with expectations, averaging approximately 600 tonnes per day for the month of February, with multiple days exceeding 700 tonnes in the latter part of the month. Ore processing rates for the first few weeks in January were constrained by minor ramp-up issues related to pumps and water balance which have now been largely resolved. Ramp-up activities are currently focused on optimization of the mill process systems with throughput and ore production trending steadily toward the design rate of 800 tonnes per day which is expected to be achieved in the coming weeks. Gold recoveries have been tracking in line with expectations at approximately 95% with both the gravity and CIP circuits performing well. Gold pours have been occurring at a rate of approximately one pour per week with regular shipments of gold doré to the Royal Canadian Mint.

Outlook for 2021

With the steady progress of mining and milling performance throughout the ramp-up period toward the design production rate of 800 tonnes per day, the Company currently anticipates declaring commercial production at the PureGold Mine in Q2 2021. Inaugural production and cost guidance for the balance of 2021 will follow shortly thereafter.

Qualified Persons and 43-101 Disclosure

Ken Donner, P. Eng., Vice President, Operations for the Company, is the designated Qualified Person for this news release within the meaning of National Instrument 43-101 (“NI 43-101”) and has reviewed and verified that the technical information contained herein is accurate and approves of the written disclosure of same.

About Pure Gold Mining Inc.

PureGold is a growth company, located in the very heart of Red Lake, Canada. Our objective is pure and simple. To develop a highly-profitable long life gold mining company, becoming Canada’s next iconic gold producer. Our plan is very disciplined, very methodical and financially sound. To expand organically, and develop PureGold’s multi-million ounce high grade gold asset incrementally, step-by-step, using a phased mining development plan to deliver maximum return.

Additional information about the Company and its activities may be found on the Company’s website at www.puregoldmining.ca and under the Company’s profile at www.sedar.com.

  1. For further information, see the technical report titled “Madsen Gold Project Technical Report Feasibility Study for the Madsen Deposit Red Lake, Ontario, Canada“ with an effective date of February 5, 2019, and dated July 5, 2019 (the “Feasibility Study”), for further information, available at puregoldmining.caor under the Company’s Sedar profile at www.sedar.com

ON BEHALF OF THE BOARD
“Darin Labrenz”
Darin Labrenz, President & CEO

Investor inquiries:

Adrian O’Brien, Director Marketing & Communications
Tel: 604-809-6890
[email protected]

NT4

Send To Friend Email Print Story

Comments are closed.

NationTalk Partners & Sponsors Learn More

CLOSE
CLOSE