Wetum Road Update 1

by ahnationtalk on January 15, 202540 Views

January 15, 2025

NORTH END

  • Road built to South Bluff (40 km)
  • Working on the road from 40 to 60 km
  • Flooding North French River; expected to get snowcats crossing by Friday the 17th
  • All small crossings built for two lane traffic
  • Working 7 days week, looking forward to the colder weather forecasted for weekend
  • Three snowcats and drags, two flooding crews
  • Expected to reach the halfway mark by Monday, January 20th

SOUTH END

  • Road built 20 km
  • Snowmobiles have reached 80 km mark
  • Crossings have been built to Little Abitibi
  • Flooding Little Abitibi River, ice at 12 inches
  • Expecting two more snowcats by Friday 17th
  • Snowcats will be operating 2 shifts by this weekend

A meeting is planned for January 21, 2025 to determine a possible opening date for Wetum Road.