NORTH END
- Road built to South Bluff (40 km)
- Working on the road from 40 to 60 km
- Flooding North French River; expected to get snowcats crossing by Friday the 17th
- All small crossings built for two lane traffic
- Working 7 days week, looking forward to the colder weather forecasted for weekend
- Three snowcats and drags, two flooding crews
- Expected to reach the halfway mark by Monday, January 20th
SOUTH END
- Road built 20 km
- Snowmobiles have reached 80 km mark
- Crossings have been built to Little Abitibi
- Flooding Little Abitibi River, ice at 12 inches
- Expecting two more snowcats by Friday 17th
- Snowcats will be operating 2 shifts by this weekend
A meeting is planned for January 21, 2025 to determine a possible opening date for Wetum Road.