Wetum Road Update 2
January 23, 2025
NORTH END
- Mainland crossing 25 inches of ice
- Drivable to 85 km, and road open to 105 km
- North French River crossing at 20 inches of ice
- Expected to be at 115 km today (Big Cedar Creek)
- Dragging with snow cats and drags from North French River to Big Cedar Creek
- Dragging 2 shifts until opening date
SOUTH END
- Drivable to Abitibi River
- Abitibi River crossing at 24 inches of ice
- Flood crew working on Little Abitibi crossing approaches and 3 creeks crossing
- Snow cat and rubber drag at Big Cedar Creek
- Working at crossing and filling in with snow
- Expecting grader and steel drag on the road by Friday of this week
- Will drag 2 shifts until opening date
Projected opening date for Wetum Road to be announced soon.